Practicing with Microsoft Certified: Dynamics 365 Supply Chain Management Functional Consultant Expert MB-335 exam dumps questions can help you build confidence and reduce exam anxiety. By familiarizing yourself with the types of questions you can expect to see on the MB-335 Microsoft Dynamics 365 Supply Chain Management Functional Consultant Expert exam and mastering the concepts and skills required to answer them, you can approach the exam with greater confidence and a sense of calm. Besides, MB-335 dumps questions can help you achieve this level of knowledge and confidence. Study free Microsoft MB-335 exam dumps below.

Page 1 of 5

1. A company produces pipe at certain fixed lengths.

The company must be able to schedule cutting machines. You set up the cutting machines as resources. AH cutting resources can produce many of the products. There are some products that require cutting machines that can produce longer lengths of product. Only some of the machines can do this.

You need to configure the resources to account for these different products.

What should you do?

2. HOTSPOT

A customer produces light projection toys for holiday decorations throughout the year.

You must implement Bills of material (BOMs) for the product lifecycle.

The solution must meet the following requirements:





You need to create a BOM for each phase.

Which BOM types should you use? To answer, select the appropriate configuration options in the answer area. NOTE: Each correct selection is worth one point.



3. HOTSPOT

A candy manufacturer uses Dynamics 365 Supply Chain Management.

A master planning run needs to prioritize the production jobs for fruit snacks by flavor and color every 16 days.

You need to configure the appropriate parameters in the coverage group.

What should you configure? To answer, select the appropriate options in the answer area. NOTE: Each correct selection is worth one point.



4. HOTSPOT

A company plans to implement routing and route postings.

You must direct positing of route cards based upon the route group at Report as finished. You set the start default order for route posting to Never and the Report as finished to Route Group Dependent. You set up the route group as shown below.





Use the drop-down menus to select the answer choice that completes each statement based on the information presented in the graphic. NOTE: Each correct selection it worth one point.



5. You need to enable the features and configuration keys for the firepits.

Which two features should you enable? Each answer presents part of the solution. NOTE: Each correct selection is worth one point

6. HOTSPOT

You need to configure scheduling for each production area.

Which scheduling options should you use? To answer, select the appropriate option in the answer area. NOTE: Each correct selection is worth one point.



7. You need to configure the system for plastic operations.

Which two parts should be manually reported as finished? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.

8. Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some question sets might have more than one correct solution, while others might not have a correct solution.

After you answer a question in this section, you will NOT be able to return to It. As a result, these questions will not appear in the review screen.

A manufacturing plant uses Lean processes. You plan to outsource a painting operation to a subcontracting vendor. You create a service item named SP-01 to represent the painting service. You need to create a subcontracting activity for the painting service.

Solution:

• Create a purchase agreement for the subcontracting vendor and add SP-01 as the painting service.

• Create a vendor resource then create a work cell for outsourced painting and add the resource to the work cell.

• Create a production flow process activity for the painting work cell and add the component to be painted as a picking activity.

• Create a server term to tie the purchase agreement to the activity.

Does the solution meet the goal?

9. You need to meet the requirements for User2.

What should you configure?

10. You work for a gem wholesaler that sells raw diamonds. Diamonds are purchased and sold in individual boxes but weighed and inventoried in carats.

You are setting up a catch weight item for diamonds. Each box of diamonds must be tracked by its individual container weight.

You need to set up this item as a full visibility catch weight item.

Which two steps must you perform? Each correct answer presents part of the solution. NOTE: Each correct selection is worth one point.


 